Vector update:
Recovery activity continues across all areas of the restoration plan. Field crews remain engaged in fibre splicing and rerouting activity. Following completion of the most concentrated splicing activity over the weekend, the remaining work is more distributed and service-specific. As a result, the restoration run rate has slowed somewhat as teams work through these more targeted fibre requirements. In parallel, our network and engineering teams continue progressing service rebuild options through alternative Vector Fibre facilities, including logical configuration and migration opportunities where technically viable. A significant focus this morning has been on building access and the associated governance requirements. Engagement continues with site control, building management and building ownership as we work to establish the safest and quickest pathway to progress the infrastructure and power-dependent elements of the recovery.