Vector update:
Recovery activity has continued to progress throughout today, with the concentrated fibre splicing and rerouting programme completing 11 planned cable batches. As the work progressed, the field restoration run rate improved, supported by the significant splice-location preparation completed earlier in the programme and the introduction of an additional field team working in parallel. The concentrated field activity planned for today has now concluded, and the field teams will stand down this evening. Vector Fibre’s engineering and network teams will continue working on the planning, design and sequencing of further fibre restoration batches for Monday. As completed field activities are translated into customer service outcomes, our NOC will continue undertaking service verification checks and associated logical configuration or migration activity where required.